dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
1 169,2 km |
2 - 8 |
20 884 mil. € |
2,9 |
3,0 |
7/2020 - 10/2021 | |||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | 149 mil. € | 1 | 1 | |||
2 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | 234 mil. € | 2 | 1 | |||
3 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 3 | 2 | |||
4 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 5 | 5 | |||
5 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | |||
6 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 | 2 | |||||
7 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 | 2 | |||||
8 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | 1 | 1 | 10/2021 | ||||
9 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | 173 mil. € | 2 | 3 | |||
10 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 3 | 3 | |||
11 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | D 26,5/120
(100) | 418 mil. € | 3 | 3 | |||
12 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | |||
13 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | |||
14 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | D 26,5/120
(100) | 192 mil. € | 2 | 2 | |||
15 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 2 | 3 | 7/2020 (0,0) | ||||
16 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 4 | 5 | |||
17 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | 517 mil. € | 2 | 3 | 1/2021 (0,0) | |||
18 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | 341 mil. € | 1 | 1 | ||||
19 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | 1 | 1 | 7/2020 (0,0) | ||||
20 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 406 mil. € | 4 | 4 | |||
21 | 1. | 10/2021 | R4 | 14,3 km | 4 | R 24,5/100 | 202 mil. € | 2 | 1 | |||
22 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 3 | 3 | |||
23 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 3 | 4 | ||||
24 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 3 | 4 | |||
25 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 2 | 4 | |||
26 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | 555 mil. € | 1 | 2 | ||||
27 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 105 mil. € | 2 | 2 | |||
28 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 4 | 4 | |||
29 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | 191 mil. € | 3 | 3 | |||
30 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 4 | 3 | |||
31 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 4 | 5 | |||
32 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 2 | 2 | |||
33 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | R 24,5/120 | 631 mil. € | 5 | 5 | |||
34 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | 142 mil. € | 2 | 2 | ||||
35 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | |||
36 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 1 | 2 | |||
37 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | D 26,5/120
(100) | 162 mil. € | 3 | 3 | |||
38 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | 179 mil. € | 1 | 3 | ||||
39 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 1 | 3 | |||
40 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | 434 mil. € | 1 | 2 | 10/2021 | |||
41 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 1 | 1 | 1/2021 (0,0) | |||
42 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | 4 | 3 | |||
43 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 4 | 3 | |||
44 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | D 26,5/100 | 60 mil. € | 5 | 5 | |||
45 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 785 mil. € | 3 | 3 | |||
46 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D 26,5/120
(100) | 136 mil. € | 4 | 3 | |||
47 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 3 | 4 | |||
48 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 235 mil. € | 1 | 1 | |||
49 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | 287 mil. € | 2 | 2 | |||
50 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | 269 mil. € | 1 | 2 | 12/2020 (0,0) | |||
51 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 410 mil. € | 1 | 1 | |||
52 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 2 | 2 | |||
53 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 2 | 2 | |||
54 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 2 | 4 | |||
55 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 4 | 4 | |||
56 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | 94 mil. € | 4 | 2 | |||
57 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 5 | 5 | |||
58 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | |||
59 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 | 4 | |||
60 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 70 mil. € | 2 | 2 | |||
61 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 4 | 3 | |||
62 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 3 | 3 | |||
63 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 4 | 4 | |||
64 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 4 | 3 | |||
65 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 3 | 5 | |||
66 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 4 | 3 | |||
67 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 2 | 3 | |||
68 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 4 | 4 | |||
69 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | 230 mil. € | 5 | 5 | |||
70 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | 129 mil. € | 3 | 2 | |||
71 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 4 | 4 | |||
72 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 2 | 4 | |||
73 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 3 | 5 | |||
74 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 12 mil. € | 2 | 1 | |||
75 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 | 3 | |||
76 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 92 mil. € | 4 | 2 | |||
77 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 122 mil. € | 2 | 2 | |||
78 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 3 | 2 | |||
79 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 4 | 3 | |||
80 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 | 5 | |||
81 | 3/2021 | R3 | 4,4 km | 2 | R 24,5/100 v polovičnom profile | 70 mil. € | 2 | 2 | ||||
82 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | R 11,5/120 | 367 mil. € | 5 | 5 | |||
83 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 5 | 4 | |||
84 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 2 | 2 | |||
85 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 4 | 4 | |||
86 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 611 mil. € | 4 | 4 | |||
87 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R 11,5/120 | 553 mil. € | 5 | 5 | |||
88 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 3 | 2 | |||
89 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 4 | 3 | |||
90 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 4 | 3 | |||
1 169,2 km |
2 - 8 |
20 884 mil. € |
2,9 |
3,0 |
7/2020 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku