dátum |
plánovaný
|
odhad NDS
|
rok
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 1/2014 | D1 | 11,3 km | 4 | 517 mil. € | 23 579 - 28 413 | 786 - 949 | 2 | 3 | 1/2014 | 1/2021 (0,0) | |||||
2 | 6/2017 | D1 | 7,9 km | 4 | 434 mil. € | 2030 | 19 072 - 21 988 | 456 - 660 | 1 | 2 | 6/2017 | 10/2021 | ||||
3 | 12/2017 | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 343 | 1 | 1 | 12/2017 | 1/2021 (0,0) | |||||
4 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 2030 | 15 837 - 18 098 | 348 - 424 | 1 | 3 | 7/2019 | |||||
5 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2031 | 9 007 - 9 998 | 288 - 316 | 2 | 2 | 8/2019 | |||||
6 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 2030 | 10 334 - 11 542 | 262 - 312 | 2 | 2 | 3/2021 | |||||
7 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 2030 | 1 698 - 6 812 | 27 - 108 | 4 | 3 | 8/2033 | ||||
8 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 2030 | 3 | 3 | 8/2034 | ||||||
73,5 km |
2 - 4 |
1 822 mil. € |
1 698 - 28 413 | 2,0 |
2,4 |
1/2014 - 8/2034 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku