dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | Lietavská Lúčka | 555 mil. € | 5,0 km | 22 691 - 32 334 | 1 | 2 | ||||||
2 | 6/2017 | D1 | 7,9 km | 4 | Prešov západ, Prešov juh | 434 mil. € | 1,9 km | 19 072 - 21 988 | 1 | 2 | 10/2021 | |||||
3 | 7/2019 | R4 | 4,3 km | 4 | Prešov - sever | 179 mil. € | 15 837 - 18 098 | 1 | 3 | |||||||
4 | 8/2019 | R2 | 13,5 km | 4 | Mýtna | 142 mil. € | 0,1 km | 9 007 - 9 998 | 2 | 2 | ||||||
5 | 3/2021 | R3 | 4,4 km | 2 | Nižná,
Nižná - sever | 70 mil. € | 0,1 km | 10 334 - 11 542 | 2 | 2 | ||||||
6 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 0,9 km | 2 | 2 | ||||||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | Turňa nad Bodvou | 117 mil. € | 0,0 km | 5 809 - 8 826 | 5 | 4 | |||||
8 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | Michalovce | 162 mil. € | -4,3 km | 10 444 - 14 783 | 3 | 3 | |||||
8 úsekov |
74,5 km |
2 - 4 |
1 736 mil. € |
3,7 km |
5 809 - 32 334 | 2,1 |
2,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku