dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 602 - 4 842 | 1 | 2 | ||||||
2 | 6/2017 | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 1 935 - 2 218 | 1 | 2 | 2/2001 | 10/2021 | ||||
3 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 964 - 1 246 | 1 | 3 | 5/2004 | |||||
4 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 1 474 - 1 473 | 2 | 2 | 11/2004 | |||||
5 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 1 307 - 1 203 | 2 | 2 | 8/2006 | |||||
6 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 6 428 - 9 084 | 876 - 1 135 | 4 | 5 | 12/2011 | ||||
7 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 5 277 - 6 250 | 977 - 1 002 | 2 | 2 | 11/2004 | ||||
8 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 1 651 | 2 | 2 | |||||
9 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 150 - 416 | 5 | 5 | 2/2016 | ||||
98,1 km |
2 - 4 |
2 212 mil. € |
2 228 - 32 334 | 2,2 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku