283,7 km |
2 - 6 |
3 940 mil. € |
4,1 |
4,1 |
||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 1 | 2 | |||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | 6,0 | |||
3 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | 7,0 | |||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 4,0 | |||
5 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 4,0 | |||
6 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 4,0 | |||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 4,0 | |||
8 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 3 | 2 | 3,0 | |||
9 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 2,0 | |||
10 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 2,0 | |||
11 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 | 5 | 1,0 | |||
12 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 230 mil. € | 5 | 5 | 4,0 | |||
13 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 | 5 | 5,0 | |||
14 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 5 | 5 | 2,0 | |||
15 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 553 mil. € | 5 | 5 | 2,0 | |||
283,7 km |
2 - 6 |
3 940 mil. € |
4,1 |
4,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku