dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 4 737 | 1 | 1 | 11/2008 | 9/2021 | ||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | |||||||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 3 057 - 7 634 | 1 | 2 | ||||||||
4 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 477 - 2 380 | 2 | 1 | 4/2008 | 12/2018 | |||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 264 - 2 380 | 3 | 3 | 4/2008 | 7/2022 | |||||
6 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 8 780 - 11 203 | 1 143 - 1 188 | 3 | 4 | 11/2003 | 6/2018 | ||||||
7 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 639 - 3 702 | 1 | 2 | ||||||||
8 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 1 039 - 1 131 | 2 | 2 | 11/2003 | 2/2018 | ||||||
9 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 399 - 500 | 1 | 3 | 5/2002 | 12/2017 | ||||||
10 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 577 - 783 | 2 | 2 | 7/1993 | 8/2017 | ||||||
10 úsekov |
96,4 km |
2 - 8 |
1 736 mil. € |
8 780 - 93 344 | 1,7 |
2,2 |
8/2017 - 7/2022 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku