✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | D1 sever | 555 mil. € | 22 691 - 32 334 | 1 | 2 | |||||||
2 | 7/2016 | R7 | 17,4 km | 4 | R7 západ | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | |||||||
3 | 7/2016 | R7 | 8,4 km | 4 | R7 západ | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | |||||||
4 | 6. | 7/2023 | R2 | 6,8 km | 4 | R2 východ | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2022 | |||||
5 | 12. | 7/2024 | R3 | 6,5 km | 2 | R3 juh | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 12/2023 | |||||
6 | 19. | 6/2025 | R4 | 8,2 km | 2 | R4 sever | 94 mil. € | 4 001 | 3 | 3 | 6/2024 | |||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 2 | 2 | 2/2025 | ||||||
8 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 2/2025 | |||||
9 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 59 mil. € | 12 862 | 3 | 4 | 2/2025 | |||||
10 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 12 157 | 3 | 4 | 4/2025 | |||||
10 úsekov |
82,8 km |
2 - 4 |
1 367 mil. € |
4 001 - 50 895 | 2,2 |
2,7 |
7/2022 - 4/2025 |
7/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku