dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||||
1 | 6. | 7/2023 | R2 | 6,8 km | 4 | 0 m | 171 mil. € | 25,1 mil. € | 12 495 - 26 580 | 11 764 - 50 895 | 3 | 3 | 8/2018 | |||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 0 m | 133 mil. € | 16,7 mil. € | 8 195 | 5 814 - 7 518 | 4 | 3 | 5/2027 | |||||
3 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 0 m | 124 mil. € | 16,6 mil. € | 7 637 | 3 769 - 3 897 | 3 | 3 | 5/2027 | |||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 0 m | 101 mil. € | 16,9 mil. € | 8 391 | 3 782 - 6 302 | 4 | 3 | 8/2027 | |||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 0 m | 182 mil. € | 16,2 mil. € | 5 938 - 12 956 | 7 234 | 4 | 3 | 2/2028 | |||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 0 m | 222 mil. € | 19,7 mil. € | 1 942 - 3 996 | 2 561 - 5 054 | 4 | 3 | 2/2028 | |||||
6 úsekov |
50,8 km |
2 - 4 |
933 mil. € |
18,4 mil. € |
2 561 - 50 895 | 3,7 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku