dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | 1 | 2023 (+1,0) | ||||||
2 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | |||||||
3 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Giraltovce, jednostranné | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2030 (+3,7) | |||||
4 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||||
5 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||||
6 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||||
6 úsekov |
103,5 km |
2 - 4 |
1 611 mil. € |
5 189 - 24 900 | 2,8 |
2,8 |
7/2023 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku