✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 541 | 3 | 3 | 3,0 | |||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 4,0 | |||||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 212 - 272 | 5 | 5 | 4,0 | |||||
4 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 381 - 551 | 2 | 4 | 6,0 | |||||
5 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 196 - 287 | 4 | 3 | 4,0 | |||||
6 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 5 098 - 5 557 | 147 - 155 | 4 | 2 | 4,0 | |||||
7 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 192 - 339 | 3 | 3 | 4,0 | |||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 153 - 173 | 5 | 5 | 4,0 | |||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 226 - 259 | 5 | 4 | 4,0 | |||||
9 úsekov |
96,5 km |
2 - 4 |
2 096 mil. € |
5 098 - 14 186 | 4,0 |
3,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku