dátum |
plánovaný
|
odhad NDS
|
na aktuálne plánovaný počet jazdných pruhov
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| |||||||||
1 | 44. - 45. | 2/2029 | 18,0 km | 2 | 176 mil. € | 151 mil. € | 5 189 - 6 389 | 5 | 5 | 7,0 | 4/2015 | 44 | ||||
2 | 44. - 45. | 2/2029 | 3,6 km | 4 | 133 mil. € | 121 mil. € | 5 | 5 | 7,0 | 9/2009 | 45 | |||||
3 | 46. | 3/2029 | 7,3 km | 4 | 321 mil. € | 300 mil. € | 10 359 | 3 | 3 | 7,0 | 46 | |||||
4 | 47. | 7/2029 | 14,0 km | 2 | 117 mil. € | 101 mil. € | 5 809 - 8 826 | 5 | 4 | 6,0 | 12/2014 | 47 | ||||
5 | 48. - 49. | 9/2029 | 9,8 km | 2 | 93 mil. € | 80 mil. € | 6 452 - 10 032 | 5 | 5 | 7,0 | 4/2015 | 48 | ||||
6 | 48. - 49. | 9/2029 | 7,9 km | 2 | 71 mil. € | 54 mil. € | 5 441 - 8 427 | 4 | 3 | 7,0 | 2/2016 | 49 | ||||
7 | 57. - 58. | 6/2031 | 14,0 km | 4 | 191 mil. € | 160 mil. € | 14 233 - 18 874 | 3 | 3 | 8,0 | 2/2016 | 57 | ||||
74,5 km |
2 - 4 |
1 102 mil. € |
967 mil. € |
5 189 - 18 874 | 4,3 |
4,0 |
44 - 57 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku