dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 272 mil. € | 5 792 - 7 064 | 192 - 224 | 714 - 765 | 3 | 2 | ||||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 176 mil. € | 5 189 - 6 389 | 153 - 173 | 787 - 807 | 5 | 5 | ||||
3 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | ||||||||
4 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 10 359 | 541 | 1 767 | 3 | 3 | |||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 117 mil. € | 5 809 - 8 826 | 226 - 259 | 881 - 1 194 | 5 | 4 | ||||
6 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6 452 - 10 032 | 212 - 272 | 780 - 984 | 5 | 5 | |||||
7 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 5 441 - 8 427 | 196 - 287 | 1 024 - 1 288 | 4 | 3 | |||||
8 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 3 | 611 mil. € | 3 247 - 11 434 | 62 - 372 | 616 - 1 456 | 4 | 4 | ||||
133,1 km |
2 - 4 |
6 |
1 794 mil. € |
3 247 - 11 434 | 4,3 |
3,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku