dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 14 625 | 2 | 2 | ||||||
2 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | Mošovce,
Horná Štubňa | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 5/2019 | |||||
3 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | Liptovská Osada | 406 mil. € | 7 784 | 4 | 4 | 4/2010 | |||||
4 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | Dargov | 418 mil. € | 9 503 - 9 802 | 3 | 3 | ||||||
5 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | Hriadky, Pozdišovce | 192 mil. € | 6 207 - 8 525 | 2 | 2 | ||||||
6 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | Sobrance | 139 mil. € | 4 033 - 8 369 | 4 | 3 | ||||||
7 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | Michalovce | 162 mil. € | 10 444 - 14 783 | 3 | 3 | ||||||
8 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | Záhor | 136 mil. € | 1 698 - 6 812 | 4 | 3 | ||||||
9 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 5 098 - 5 557 | 4 | 2 | 9/2010 | ||||||
9 úsekov |
107,7 km |
2 - 4 |
1 719 mil. € |
1 698 - 14 783 | 3,3 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku