dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 157 m | 63 mil. € | 3 | 2 | 14,3 | 4/2026 | 16. | |||
2 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 110 m | 71 mil. € | 4 | 3 | 14,3 | 2/2028 | 11. | |||
3 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 428 m | 406 mil. € | 4 | 4 | 13,0 | 6/2029 | 11. | |||
4 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 366 m | 339 mil. € | 4 | 4 | 13,0 | 6/2029 | 11. | |||
5 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 3 | 3 | 25,0 | 8/2031 | 15. | |||
6 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 2 | 2 | 24,0 | 8/2031 | 12. | |||
7 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 213 m | 139 mil. € | 4 | 3 | 24,0 | 8/2031 | 13. | |||
8 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 3 | 3 | 24,0 | 8/2031 | 13. | |||
9 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 4 | 3 | 24,0 | 8/2031 | 67. | |||
108,0 km |
2 - 4 |
2 192 m |
1 925 mil. € |
3,4 |
3,0 |
11. - 67. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku