dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 500 - 623 | 4 | 5 | 1/2013 | 7/2021 | |||
2 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 423 - 703 | 4 | 3 | 1/2021 | 7/2025 | |||
3 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 537 | 4 | 4 | 10/2010 | 5/2028 | |||
4 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 633 - 797 | 4 | 4 | 10/2010 | 5/2028 | |||
5 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 940 - 1 697 | 2 | 2 | 3/2009 | 5/2027 | |||
6 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 678 - 730 | 3 | 3 | 3/1998 | 9/2028 | |||
7 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 404 - 665 | 2 | 2 | 4/1998 | 9/2028 | |||
8 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 217 - 330 | 4 | 3 | 3/1999 | 9/2028 | |||
9 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 659 - 820 | 3 | 3 | 3/1999 | 9/2028 | |||
10 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 70 - 361 | 4 | 3 | 3/1999 | 9/2028 | |||
129,9 km |
2 - 4 |
2 340 mil. € |
3,4 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku