dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
1 | 8. - 9. | 3/2024 | R2 | 6,2 km | 105 mil. € | 2 | 2 | 3/2024 | 3/2026 (+4,7) | |||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 176 mil. € | 5 | 5 | 2/2029 | 2/2032 (+4,9) | |||
3 | 48. - 49. | 9/2029 | R3 | 7,9 km | 71 mil. € | 4 | 3 | 9/2029 | 9/2032 (+4,1) | |||
4 | 55. - 56. | 5/2031 | R1 | 11,5 km | 406 mil. € | 4 | 4 | 5/2031 | 5/2033 (+10,2) | |||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 339 mil. € | 4 | 4 | 5/2031 | 5/2033 (+10,2) | |||
6 | 64. - 68. | 8/2033 | D1 | 12,6 km | 418 mil. € | 3 | 3 | 8/2033 | 8/2036 (+7,9) | |||
7 | 64. - 68. | 8/2033 | D1 | 18,2 km | 192 mil. € | 2 | 2 | 8/2033 | 8/2036 (+7,9) | |||
8 | 64. - 68. | 8/2033 | D1 | 15,8 km | 139 mil. € | 4 | 3 | 8/2033 | 8/2036 (+7,7) | |||
9 | 64. - 68. | 8/2033 | D1 | 12,1 km | 162 mil. € | 3 | 3 | 8/2033 | 8/2036 (+7,7) | |||
10 | 64. - 68. | 8/2033 | D1 | 15,5 km | 136 mil. € | 4 | 3 | 8/2033 | 8/2036 (+7,7) | |||
127,2 km |
2 143 mil. € |
3,5 |
3,2 |
3/2024 - 8/2033 |
3/2026 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku