dátum |
plánovaný
|
odhad NDS
|
rok
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 13 069 | 2030 | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | ||||
2 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 10 984 | 2030 | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | ||||
3 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 60 m | 305 mil. € | 10 765 | 2030 | 3 | 3 | 8/2037 (+5,9) | |||||
4 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 213 m | 139 mil. € | 6 464 | 2030 | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | ||||
5 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | NDS údaj neposkytla | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | ||||||
6 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 295 m | 662 mil. € | 8 772 - 13 803 | 2030 | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
7 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 7 061 | 2030 | 10 444 - 14 783 | 3 | 3 | 8/2036 (+7,7) | ||||
8 | 11. | 6/2024 | R1 | 2,7 km | 4 | 131 m | 155 mil. € | 18 855 | 2030 | 16 268 | 4 | 3 | 6/2026 (+3,5) | ||||
9 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 2 689 | 2030 | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | ||||
9 úsekov |
194,7 km |
2 - 4 |
1 617 m |
3 189 mil. € |
1 698 - 16 268 | 3,3 |
3,2 |
6/2026 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku