dátum |
plánovaný
|
odhad NDS
|
podľa údajov NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 5,0 | 11/2004 | 8/2028 (+5,1) | ||||||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 5,0 | 12/2009 | 9/2032 (+5,6) | |||||
3 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 3,0 | 4/2010 | 6/2036 (+2,3) | ||||||
4 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 2,0 | 8/2036 (+7,9) | |||||||
5 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 2,0 | 8/2036 (+7,9) | |||||||
6 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 2,0 | 8/2036 (+7,7) | |||||||
7 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 2,0 | 8/2036 (+7,7) | |||||||
8 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 2,0 | 8/2036 (+7,7) | |||||||
9 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 2,0 | 2/2020 | 8/2037 (+5,9) | |||||||
10 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 2,0 | 10/2004 | 8/2037 (+5,9) | ||||||
10 úsekov |
222,5 km |
2 - 6 |
3 479 mil. € |
1 698 - 54 519 | 3,3 |
3,2 |
8/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku