dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | Čerbrať - z pôv. 2026 m sa predĺži na cca 3600 m | 341 mil. € | 1 | 1 | 7/2008 | ||||||
2 | 6/2014 | D1 | 13,5 km | 4 | Višňové 7445 m | 555 mil. € | 1 | 2 | 9/2008 | ||||||
3 | 7/2019 | R4 | 4,3 km | 4 | Bikoš 1153 m | 179 mil. € | 1 | 3 | 8/2016 | ||||||
4 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 6/2018 | |||||||
5 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | ||||||||
6 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 2/2012 | |||||||
7 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 7/2019 | ||||||
8 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 3/2019 | ||||||
9 | 4. | 9/2022 | R4 | 10,2 km | 4 | Okruhliak 1917 m | 299 mil. € | 1 | 3 | 5/2021 | |||||
10 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | - 0,8 % (B. Bystrica - Ružomberok) | 4 | 3 | 4/2023 | |||||
10 úsekov |
90,5 km |
2 - 8 |
2 360 mil. € |
1,8 |
2,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku