dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
12 úsekov |
113,8 km |
2 - 8 |
2 855 mil. € |
2 552 - 62 652 | 2,7 |
3,1 |
||||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 4 737 | 1 | 1 | 8,0 | ||||
2 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 1 263 | 3 | 4 | 7,0 | |||||
3 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 105 - 2 649 | 2 | 4 | 6,0 | |||||
4 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 863 - 1 016 | 4 | 4 | 5,0 | |||||
5 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 2 661 - 2 869 | 1 | 1 | 7,0 | |||||
6 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 1 056 | 2 | 2 | 5,0 | |||||
7 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 655 - 822 | 4 | 4 | 5,0 | |||||
8 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 693 | 4 | 3 | 3,0 | |||||
9 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 2 660 | 1 | 2 | 7,0 | |||||
10 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 4,0 | |||||||
11 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 792 - 846 | 3 | 5 | 5,0 | |||||
12 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 709 - 1 316 | 4 | 3 | 4,0 | |||||
12 úsekov |
113,8 km |
2 - 8 |
2 855 mil. € |
2 552 - 62 652 | 2,7 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku