dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
5 - vysoko predražená, 1 - veľmi nízka
| |||||||||
34 úsekov |
333,4 km |
2 - 8 |
7 914 mil. € |
2,8 |
3,1 |
||||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | D1 západ | 149 mil. € | 1 | 1 | ||||||
2 | 5. | 4/2023 | R1 | 8,1 km | 4 | R1 BB - RK | 173 mil. € | 2 | 3 | ||||||
3 | 7. | 2/2024 | D1 | 13,5 km | 4 | D1 sever | Švošov | 1 235 mil. € | 1 | 1 | |||||
4 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R7 západ | Dunajská Streda | 191 mil. € | 4 | 5 | |||||
5 | 11. | 6/2024 | R1 | 2,7 km | 4 | R1 BB - RK | 155 mil. € | 4 | 3 | ||||||
6 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R7 západ | 227 mil. € | 4 | 4 | ||||||
7 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R7 západ | Nové Zámky | 172 mil. € | 4 | 4 | |||||
8 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R7 západ | 161 mil. € | 4 | 5 | ||||||
9 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R2 východ | Jablonov nad Turňou (pôjde ako samostatná stavba) | 272 mil. € | 3 | 2 | |||||
10 | 19. | 6/2025 | R4 | 8,2 km | 2 | R4 sever | 94 mil. € | 3 | 3 | ||||||
11 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 2 | 2 | ||||||
12 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 2 | 3 | ||||||
13 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R2 západ | 277 mil. € | 2 | 2 | ||||||
14 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 59 mil. € | 3 | 4 | ||||||
15 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 3 | 4 | ||||||
16 | 25. | 1/2026 | D3 | 10,8 km | 4 | D3 Kysuce | Oščadnica | 309 mil. € | 2 | 4 | |||||
17 | 26. | 4/2026 | R2 | 20,7 km | 2 | R2 stred | 211 mil. € | 4 | 4 | ||||||
18 | 27. | 5/2026 | D3 | 11,2 km | 4 | D3 Kysuce | 410 mil. € | 1 | 1 | ||||||
19 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R4 stred | 105 mil. € | 2 | 2 | ||||||
20 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R2 stred | 125 mil. € | 4 | 4 | ||||||
21 | 30. | 10/2026 | R1 | 4,6 km | 4 | R1 BB - RK | 100 mil. € | 4 | 3 | ||||||
22 | 31. | 11/2026 | D3 | 4,0 km | 4 | D3 Kysuce | 179 mil. € | 1 | 2 | ||||||
23 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D4 sever | 772 mil. € | 3 | 4 | ||||||
24 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R2 východ | 224 mil. € | 3 | 5 | ||||||
25 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D1 západ | 234 mil. € | 2 | 1 | ||||||
26 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R4 sever | 116 mil. € | 2 | 3 | ||||||
27 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R4 sever | 122 mil. € | 2 | 2 | ||||||
28 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R2 východ | 73 mil. € | 5 | 4 | ||||||
29 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D1 západ | úprava SSÚD Trnava | 321 mil. € | 3 | 2 | |||||
30 | 41. | 9/2028 | R2 | 11,5 km | 2 | R2 západ | 235 mil. € | 2 | 4 | ||||||
31 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D4 sever | 133 mil. € | 5 | 5 | ||||||
32 | 46. | 3/2029 | D1 | 7,3 km | 4 | D1 sever | Beharovce (úprava velína) | 321 mil. € | 3 | 3 | |||||
33 | 59. | 7/2031 | R2 | 17,5 km | 4 | R2 stred | Zvolenská Slatina | 287 mil. € | 2 | 2 | |||||
34 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | D3 Kysuce | 54 mil. € | 3 | 4 | ||||||
34 úsekov |
333,4 km |
2 - 8 |
7 914 mil. € |
2,8 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku