dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
22 úsekov |
260,7 km |
2 - 8 |
28 |
6 937 mil. € |
2,8 |
2,6 |
7/2023 - po 2040 | |||||||
1 | 12/2013 | D1 | 14,9 km | 4 | 3 | 341 mil. € | 926 - 1 852 | 1 | 1 | 2023 (+1,0) | ||||
2 | 6/2014 | D1 | 13,5 km | 4 | 1 | 555 mil. € | 1 254 - 2 069 | 1 | 2 | 2024 (+4,0) | ||||
3 | 3. | 3/2022 | D1 | 3,5 km | 8 | 1 | 149 mil. € | 4 281 | 1 | 1 | 9/2025 (+4,6) | |||
4 | 5. | 4/2023 | R1 | 8,1 km | 4 | 1 | 173 mil. € | 775 - 1 059 | 2 | 3 | 4/2026 (+3,7) | |||
5 | 7. | 2/2024 | D1 | 13,5 km | 4 | 2 | 1 235 mil. € | 869 - 1 422 | 1 | 1 | 12/2030 (+4,5) | |||
6 | 10. | 4/2024 | D1 | 3,8 km | 2 | 0 | 57 mil. € | 531 | 3 | 5 | 4/2027 (+4,1) | |||
7 | 11. | 6/2024 | R1 | 2,7 km | 4 | 2 | 155 mil. € | 893 | 4 | 3 | 6/2026 (+3,5) | |||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 0 | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | ||||
9 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | ||||
10 | 30. | 10/2026 | R1 | 4,6 km | 4 | 1 | 100 mil. € | 623 | 4 | 3 | 10/2028 (+3,5) | |||
11 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 1 | 234 mil. € | 4 281 | 2 | 1 | 6/2030 (+6,9) | |||
12 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 2 | 785 mil. € | 575 - 1 052 | 3 | 3 | 2/2031 (+6,9) | |||
13 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 2 | 321 mil. € | 2 765 - 3 271 | 3 | 2 | 9/2032 (+5,6) | |||
14 | 46. | 3/2029 | D1 | 7,3 km | 4 | 0 | 321 mil. € | 974 | 3 | 3 | 9/2033 (+5,8) | |||
15 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 1 | 406 mil. € | 537 | 4 | 4 | 5/2033 (+10,2) | |||
16 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 0 | 339 mil. € | 633 - 797 | 4 | 4 | 5/2033 (+10,2) | |||
17 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 1 | 418 mil. € | 678 - 730 | 3 | 3 | 8/2036 (+7,9) | |||
18 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 2 | 192 mil. € | 404 - 665 | 2 | 2 | 8/2036 (+7,9) | |||
19 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 1 | 139 mil. € | 217 - 330 | 4 | 3 | 8/2036 (+7,7) | |||
20 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 1 | 162 mil. € | 659 - 820 | 3 | 3 | 8/2036 (+7,7) | |||
21 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 1 | 136 mil. € | 70 - 361 | 4 | 3 | 8/2036 (+7,7) | |||
22 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 4 | 631 mil. € | 469 - 796 | 5 | 5 | po 2040 | |||
22 úsekov |
260,7 km |
2 - 8 |
28 |
6 937 mil. € |
2,8 |
2,6 |
7/2023 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku