1 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 535 mil. € | 18,5 km | 22 691 - 32 334 | 1 | 2 | ||||||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 127 mil. € | 62 652 | . . . | 1 | 1 | |||||
3 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 263 mil. € | 22 341 - 30 731 | 1 | 3 | ||||||
4 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 52 mil. € | 10 312 | 3 | 5 | ||||||
5 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 118 mil. € | 8,9 km | 5 814 - 7 518 | 4 | 3 | |||||
6 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 110 mil. € | 8,3 km | 3 769 - 3 897 | 3 | 3 | |||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 87 mil. € | 6,3 km | 3 782 - 6 302 | 4 | 3 | |||||
8 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 161 mil. € | 7 234 | 4 | 3 | ||||||
9 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 199 mil. € | 2 561 - 5 054 | 4 | 3 | ||||||
9 úsekov |
75,0 km |
2 - 8 |
1 823 mil. € |
1 651 mil. € |
42,0 km |
2 561 - 62 652 | 2,8 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku