dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
24 úsekov |
215,0 km |
2 - 8 |
5 227 mil. € |
109,9 km |
2,4 |
2,8 |
||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 10,0 | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 13,5 km | 2 | 2 | 9,0 | |||||
3 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 9,2 km | 3 | 4 | 7,0 | |||||
4 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 5,4 km | 2 | 2 | 11,0 | |||||
5 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 10,0 | |||||
6 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 8,0 | |||||
7 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 10,0 | |||||
8 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 9,0 | |||||
9 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 9,0 | |||||
10 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 13,5 km | 1 | 1 | 7,0 | ||||
11 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 6,2 km | 2 | 2 | 8,0 | ||||
12 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 9,4 km | 4 | 5 | 6,0 | ||||
13 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 3 | 5 | 8,0 | |||||
14 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | 6,0 | |||||
15 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 8,3 km | 2 | 2 | 8,0 | ||||
16 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 5,0 | |||||
17 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 6,0 | |||||
18 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 4 | 5 | 5,0 | |||||
19 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 14,1 km | 3 | 2 | 8,0 | ||||
20 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7,0 | |||||
21 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 10,8 km | 2 | 4 | 6,0 | ||||
22 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 11,2 km | 1 | 1 | 7,0 | ||||
23 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 8,3 km | 4 | 3 | 4,0 | ||||
24 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 3 | 4 | 4,0 | |||||
24 úsekov |
215,0 km |
2 - 8 |
5 227 mil. € |
109,9 km |
2,4 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku