plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
282,6 km |
2 - 6 |
3 290 mil. € |
1 065 - 44 493 | 4,3 |
4,3 |
||||||||
1 | R7 | 6,4 km | 4 - 6 | 27 633 - 44 493 | . . . | 1 | 1 | 6/2017 | 10/2021 | ||||
2 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 11/2023 | ||||||
3 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 7/2022 | 2/2025 | ||||
4 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 12/2021 | 2/2025 | ||||
5 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 2/2026 | |||||
6 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 1/2027 | |||||
7 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 6/2028 | ||||||
8 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2027 | |||||
9 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2027 | |||||
10 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 1/2031 | ||||
11 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 1/2031 | ||||||
12 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 5 | 5 | ||||||
13 | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | ||||||
14 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | ||||||
15 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | ||||||
16 | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | ||||||
282,6 km |
2 - 6 |
3 290 mil. € |
1 065 - 44 493 | 4,3 |
4,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku