plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
292,0 km |
2 - 6 |
3 208 mil. € |
1 065 - 32 968 | 4,7 |
4,7 |
4/2028 - po 2040 |
|||||||
1 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 6/2016 | 12/2029 | ||||
2 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 6/2016 | 7/2032 | ||||
3 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2016 | 2/2032 | ||||
4 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | 2/2016 | po 2040 | ||||
5 | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | 9/2015 | po 2040 | ||||
6 | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | 12/2011 | po 2040 | ||||
7 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 8/2010 | 2/2033 | |||||
8 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2009 | 9/2032 | ||||
9 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 9/2009 | 2/2031 | ||||
10 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 10/2006 | 4/2028 | ||||
11 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 11/2003 | 12/2028 | ||||
12 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 | ||||
13 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 5 | 5 | po 2040 | |||||
14 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | po 2040 | |||||
15 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 | ||||||
292,0 km |
2 - 6 |
3 208 mil. € |
1 065 - 32 968 | 4,7 |
4,7 |
4/2028 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku