dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | ||||||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 189 - 6 389 | 5 | 5 | |||||
3 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | |||||
4 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 32 968 | . . . | 5 | 5 | ||||
5 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | ||||||
6 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | ||||||
7 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 5 762 - 14 648 | 4 | 4 | |||||
8 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | R 11,5/70 | 54 mil. € | 7 972 | 3 | 4 | |||||
8 úsekov |
166,5 km |
2 - 6 |
2 556 mil. € |
4 151 - 32 968 | 3,8 |
4,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku