dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 25. | 1/2026 | 10,8 km | 4 | 309 mil. € | 25,7 mil. € | 14 176 - 14 186 | 2 | 4 | 7/1996 | 5/2025 | ||||
2 | 26. | 4/2026 | 20,7 km | 2 | 211 mil. € | 9,3 mil. € | 6 969 - 10 726 | 4 | 4 | 11/2004 | 11/2024 | ||||
3 | 27. | 5/2026 | 11,2 km | 4 | 410 mil. € | 33,0 mil. € | 13 886 - 21 743 | 1 | 1 | 7/1996 | 7/2025 | ||||
4 | 28. - 29. | 8/2026 | 4,0 km | 4 | 105 mil. € | 21,8 mil. € | 14 625 | 2 | 2 | 7/2004 | 11/2024 | ||||
5 | 28. - 29. | 8/2026 | 10,6 km | 2 | 125 mil. € | 10,8 mil. € | 6 412 - 8 112 | 4 | 4 | 10/2000 | 6/2025 | ||||
6 | 30. | 10/2026 | 4,6 km | 4 | 100 mil. € | 19,7 mil. € | 11 611 | 4 | 3 | 9/2009 | 6/2026 | ||||
7 | 31. | 11/2026 | 4,0 km | 4 | 179 mil. € | 40,9 mil. € | 15 053 | 1 | 2 | 7/1996 | 5/2025 | ||||
8 | 32. - 33. | 12/2026 | 12,4 km | 4 | 772 mil. € | 59,4 mil. € | 3 | 4 | 8/2007 | ||||||
9 | 32. - 33. | 12/2026 | 18,0 km | 2 | 224 mil. € | 10,5 mil. € | 10 140 - 11 010 | 3 | 5 | 5/2008 | 3/2025 | ||||
10 | 62. - 63. | 10/2032 | 6,9 km | 6 | 107 mil. € | 14,2 mil. € | 5 | 5 | 11/2009 | 4/2031 | |||||
103,2 km |
2 - 6 |
2 542 mil. € |
22,5 mil. € |
6 412 - 21 743 | 2,9 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku