dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 12/2019 | 12/2019 | 5 | ||||||
2 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 0,0 km | 5 304 | 2 | 2 | 12/2019 | 3/2023 | 8 | |||||
3 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 0,0 km | 14 176 - 14 186 | 2 | 4 | 8/2010 | 7/2022 | 25 | |||||
4 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | -1,6 km | 10 140 - 11 010 | 3 | 5 | 12/2023 | 9/2025 | 33 | |||||
5 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 0,0 km | 15 053 | 1 | 2 | 12/2021 | 1/2026 | 31 | |||||
6 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 10/2014 | 11/2020 | 4 | ||||||
7 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 3,4 km | 5 792 - 7 064 | 3 | 2 | 6/2018 | 1/2023 | 17 | |||||
8 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 0,0 km | 5 277 - 6 250 | 2 | 2 | 3/2020 | 8/2023 | 13 | |||||
9 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 0,1 km | 13 886 - 21 743 | 1 | 1 | 2000/ 2007/ 2011 | 5/2022 | 27 | |||||
9 úsekov |
90,9 km |
2 - 4 |
2 141 mil. € |
1,9 km |
5 277 - 30 731 | 1,9 |
2,7 |
4 - 33 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku