dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 6 403 - 9 478 | 4 | 5 | 16 | 5/2029 (+3,5) | |||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 22 | 10/2028 (+3,2) | |||||
3 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 23 | 10/2028 (+4,2) | |||||
4 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 24 | 12/2028 (+4,3) | |||||
5 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 31 | 11/2030 (+6,4) | |||||
6 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 36 | 6/2030 (+3,7) | |||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 52 | 5/2033 (+6,1) | |||||
8 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | 76 | po 2040 (0,0) | |||||
8 úsekov |
78,9 km |
2 - 4 |
1 264 mil. € |
2 156 - 15 053 | 3,0 |
3,5 |
16 - 76 |
10/2028 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku