dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 15 m | 191 mil. € | 4,6 mil. € | 6 428 - 9 084 | 4 | 5 | 10/2005 | ostatné | |||||
2 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 433 m | 191 mil. € | 4,8 mil. € | 14 233 - 18 874 | 3 | 3 | 5/2008 | variant TEN-T | |||||
3 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 16,4 mil. € | 5 713 - 13 545 | 5 | 5 | 4/2010 | |||||||
4 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 336 m | 230 mil. € | 5,5 mil. € | 2 156 - 6 890 | 5 | 5 | 10/2005 | ostatné | |||||
5 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 300 m | 92 mil. € | 2,1 mil. € | 5 098 - 5 557 | 4 | 2 | 5/2008 | variant TEN-T | |||||
6 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 0,0 mil. € | 5 420 - 8 693 | 5 | 5 | 6/2009 | |||||||
7 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 128 m | 54 mil. € | 1,5 mil. € | 7 972 | 3 | 4 | 2/2007 | ostatné | |||||
8 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 1 114 m | 367 mil. € | 9,1 mil. € | 2 228 - 6 331 | 5 | 5 | 10/2005 | ostatné | |||||
9 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 2 619 m | 611 mil. € | 16,2 mil. € | 3 247 - 11 434 | 4 | 4 | 6/2008 | variant TEN-T | |||||
10 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 1 130 m | 553 mil. € | 14,6 mil. € | 1 065 - 4 239 | 5 | 5 | 10/2005 | ostatné | |||||
10 úsekov |
272,5 km |
2 - 4 |
6 075 m |
2 980 mil. € |
74,7 mil. € |
1 065 - 18 874 | 4,3 |
4,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku