dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 181 | 2 | 2 | 12/2023 | 8/2025 | |||||
2 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 62 652 | . . . | 530 | 2 | 1 | 6/2016 | 10/2026 | ||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 49 - 72 | 5 | 5 | 1/2026 | 2/2028 | |||||
4 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 6/2028 | ||||||||
5 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 51 | 3 | 3 | 6/2024 | 7/2028 | |||||
6 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 56 - 84 | 5 | 4 | 7/2026 | 7/2028 | |||||
7 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 69 - 107 | 5 | 5 | 9/2026 | 9/2028 | |||||
8 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 30 - 78 | 4 | 3 | 2/2027 | 1/2029 | |||||
9 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 42 - 55 | 3 | 3 | 5/2027 | 5/2029 | |||||
9 úsekov |
82,6 km |
2 - 8 |
1 373 mil. € |
3 769 - 62 652 | 3,8 |
3,4 |
8/2025 - 5/2029 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku