dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 62 652 | . . . | 2 | 1 | 5/2010 | 6/2027 | ||||
2 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 12/2017 | 12/2017 | 6/2027 | ||||
3 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 3 407 - 3 769 | 2 | 2 | 12/2017 | 12/2017 | 6/2027 | ||||
4 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 10/2010 | 12/2025 | 5/2031 | ||||
5 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 7/2020 | 1/2026 | 10/2032 | |||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 7/2019 | 1/2026 | 10/2032 | |||||
49,0 km |
2 - 8 |
1 008 mil. € |
3 407 - 62 652 | 3,3 |
3,3 |
6/2027 - 10/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku