dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 10 990 m | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 0 m | 133 mil. € | 5 814 - 7 518 | 384 - 424 | 4 | 3 | 5/2033 (+6,1) | ||||
3 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 0 m | 191 mil. € | 14 233 - 18 874 | 911 - 1 315 | 3 | 3 | 6/2034 (+7,0) | ||||
4 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 1 150 m | 662 mil. € | 5 762 - 14 648 | 525 - 852 | 4 | 4 | 8/2037 (+5,9) | ||||
5 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 4 780 m | 785 mil. € | 8 140 - 13 204 | 575 - 1 052 | 3 | 3 | 2/2031 (+6,9) | ||||
5 úsekov |
98,3 km |
2 - 4 |
16 920 m |
2 543 mil. € |
5 762 - 18 874 | 3,4 |
3,4 |
2/2031 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku