dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 2,5 km | 12 862 | 3 | 4 | 10/2028 (+4,2) | ||||
2 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 18,0 km | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | ||||
3 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 2/2031 (+6,9) | |||||
4 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 4 | 5/2033 (+10,2) | |||||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 5/2033 (+10,2) | |||||
6 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | |||||
7 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 16,0 km | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | ||||
8 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 8,7 km | 7 211 | 4 | 2 | 8/2034 (+2,1) | ||||
9 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 10,9 km | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | ||||
9 úsekov |
148,6 km |
2 - 4 |
3 343 mil. € |
56,1 km |
4 151 - 29 988 | 3,2 |
3,4 |
10/2028 - 6/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku