dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 31. | 11/2026 | D3 | 4,0 km | 4 | Horelica 590 m | 179 mil. € | 15 053 | 1 | 2 | 11/2030 (+6,4) | |||||
2 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||||
3 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||||
7 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | Biely Potok 1400 m | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 5/2033 (+10,2) | |||||
7 úsekov |
59,3 km |
2 - 4 |
1 239 mil. € |
2 561 - 15 053 | 3,6 |
3,3 |
11/2030 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku