dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R4 sever | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2029 | |||||
2 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R4 sever | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2026 | |||||
3 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 12 157 | 3 | 4 | 4/2025 | |||||
4 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 59 mil. € | 12 862 | 3 | 4 | 2/2025 | |||||
5 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 2 | 2 | 2/2025 | ||||||
6 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 2/2025 | |||||
7 | 12. | 7/2024 | R3 | 6,5 km | 2 | R3 juh | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 12/2023 | |||||
7 úsekov |
41,0 km |
2 - 4 |
764 mil. € |
3 782 - 12 862 | 2,6 |
3,0 |
12/2023 - 5/2029 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku