dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 13,0 min. | 9 654 - 12 079 | 2 | 2 | 10/2005 | 10/2028 (+3,2) | |||||
2 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 11,0 min. | 7 793 | 2 | 4 | 2/2006 | 9/2031 (+5,4) | |||||
3 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 1/2021 | 9/2032 (+4,1) | ||||||
4 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 14,0 min. | 12 819 - 29 988 | 2 | 2 | 3/2009 | 7/2034 (+10,0) | |||||
5 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 7,5 min. | 7 211 | 4 | 2 | 8/2024 | 8/2034 (+2,1) | |||||
6 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 11,5 min. | 5 586 - 10 745 | 3 | 2 | 8/2024 | 8/2034 (+2,1) | |||||
6 úsekov |
72,5 km |
2 - 4 |
1 093 mil. € |
57,0 min. |
5 441 - 29 988 | 2,8 |
2,5 |
10/2028 - 8/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku