dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 86 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | žiadna | |||||
2 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 199 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | žiadna | |||||
3 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 164 m | 129 mil. € | 2 552 - 2 737 | 4 | 3 | žiadna | |||||
4 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 2 | Vypracúva sa dokumentácia na stavebné povolenie. | ||||||
5 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 433 m | 191 mil. € | 14 233 - 18 874 | 3 | 3 | žiadna | |||||
6 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 449 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | žiadna | |||||
7 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | žiadna | ||||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 226 m | 176 mil. € | 5 189 - 6 389 | 5 | 5 | žiadna | |||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | 123 m | 117 mil. € | 5 809 - 8 826 | 5 | 4 | žiadna | |||||
9 úsekov |
92,2 km |
2 - 4 |
1 679 m |
1 128 mil. € |
2 552 - 18 874 | 3,8 |
3,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku