dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 3/2022 | 7/2026 (+4,3) | ||||||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 1/2027 | 2/2032 (+4,9) | |||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2028 | 5/2033 (+6,1) | ||||||
4 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené | 305 mil. € | 3 | 3 | 2/2033 | 8/2037 (+5,9) | ||||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 2/2033 | 8/2037 (+5,9) | ||||||
5 úsekov |
93,8 km |
2 - 4 |
1 415 mil. € |
3 782 - 50 895 | 3,8 |
3,6 |
7/2026 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku