dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
330,0 km |
2 - 6 |
5 122 mil. € |
1 065 - 54 519 | 3,3 |
3,2 |
||||||||||
1 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 5 792 - 7 064 | 714 - 765 | 3 | 2 | 8,0 | ||||
2 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 1 651 | 2 | 2 | 5,0 | ||||
3 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 1 245 - 1 287 | 3 | 5 | 5,0 | ||||
4 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 6 651 - 9 113 | 750 - 771 | 2 | 3 | 5,0 | ||||
5 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 3 407 - 3 769 | 1 298 - 1 289 | 2 | 2 | 5,0 | ||||
6 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 711 | 5 | 4 | 4,0 | ||||
7 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 862 - 4 344 | 3 | 2 | 5,0 | |||
8 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 1 259 | 2 | 4 | 5,0 | ||||
9 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 1 767 | 3 | 3 | 3,0 | ||||
10 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 1 024 - 1 288 | 4 | 3 | 4,0 | ||||
11 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 940 | 4 | 4 | 3,0 | ||||
12 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 975 - 1 570 | 4 | 4 | 3,0 | ||||
13 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 1 901 - 3 009 | 2 | 2 | 5,0 | ||||
14 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 9 503 - 9 802 | 870 - 911 | 3 | 3 | 2,0 | ||||
15 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 911 - 840 | 2 | 2 | 2,0 | ||||
16 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 461 - 640 | 4 | 3 | 2,0 | ||||
17 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 876 - 901 | 3 | 3 | 2,0 | ||||
18 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 242 - 519 | 4 | 3 | 2,0 | ||||
19 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 644 - 1 514 | 5 | 5 | 1,0 | ||||
20 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 144 - 733 | 5 | 5 | 2,0 | ||||
330,0 km |
2 - 6 |
5 122 mil. € |
1 065 - 54 519 | 3,3 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku