dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 170,0 mil. € | 15 837 - 18 098 | 213 - 312 | 964 - 1 246 | 1 | 3 | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 161,8 mil. € | 5,0 min. | 9 007 - 9 998 | 51 - 106 | 1 474 - 1 473 | 2 | 2 | |||||
3 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 75,0 mil. € | 3,6 min. | 10 334 - 11 542 | 230 - 281 | 1 307 - 1 203 | 2 | 2 | |||||
4 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 90 - 464 | 904 - 3 909 | 2 | 1 | ||||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 169 - 482 | 770 - 3 909 | 3 | 3 | ||||||
6 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 1,9 min. | 6 969 - 10 726 | 44 - 143 | 1 217 - 1 494 | 4 | 4 | |||||
64,0 km |
2 - 4 |
975 mil. € |
406,7 mil. € |
10,5 min. |
6 969 - 50 895 | 2,3 |
2,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku