dátum |
plánovaný
|
odhad NDS
|
rok
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 337 m | 179 mil. € | 2030 | 15 837 - 18 098 | 1 | 3 | 1.3.2012 | 12/2017 | |||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2031 | 9 007 - 9 998 | 2 | 2 | 1.6.2017 | 2/2018 | ||||||
3 | 3/2021 | R3 | 4,4 km | 2 | 135 m | 70 mil. € | 2030 | 10 334 - 11 542 | 2 | 2 | 07/2010 | 8/2017 | |||||
4 | 1. | 10/2021 | R4 | 14,3 km | 4 | 365 m | 202 mil. € | 2025 | 10 088 - 50 895 | 2 | 1 | 11/2013 | 12/2018 | ||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 169 m | 171 mil. € | 2035 | 11 764 - 50 895 | 3 | 3 | 11/2013 | 7/2022 | ||||
6 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 164 m | 129 mil. € | 2030 | 5 586 - 10 745 | 3 | 2 | nezačaté | 12/2030 | ||||
54,2 km |
2 - 4 |
2 170 m |
893 mil. € |
5 586 - 50 895 | 2,2 |
2,2 |
8/2017 - 12/2030 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku