dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 213 - 312 | 1 | 3 | 2023 (+2,0) | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 51 - 106 | 2 | 2 | 2021 (+1,1) | ||||||
3 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 230 - 281 | 2 | 2 | 8/2022 (+2,2) | ||||||
4 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 90 - 464 | 2 | 1 | 10/2024 (+2,6) | |||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 169 - 482 | 3 | 3 | 7/2026 (+4,3) | |||||
6 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 3 407 - 3 769 | 42 - 71 | 2 | 2 | 6/2030 (+3,7) | |||||
7 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 5 586 - 10 745 | 72 - 223 | 3 | 2 | 8/2034 (+2,1) | |||||
61,2 km |
2 - 4 |
1 016 mil. € |
3 407 - 50 895 | 2,1 |
2,1 |
7/2021 - 8/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku