dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
12 úsekov |
253,1 km |
2 - 6 |
2 193 mil. € |
3,8 |
3,9 |
7/2020 - 10/2021 | ||||||||
1 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 2 | 3 | 12/2013 | 7/2020 (0,0) | |||||
2 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | 1 | 1 | 5/2015 | 7/2020 (0,0) | |||||
3 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | 1 | 1 | 2/2017 | 10/2021 | |||||
4 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 4 | 5 | |||||
5 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 4 | 4 | |||||
6 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 4 | 4 | |||||
7 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 4 | 5 | |||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 176 mil. € | 5 | 5 | 1/2026 | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 5 | 4 | 7/2026 | ||||
10 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | 230 mil. € | 5 | 5 | |||||
11 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | R 11,5/120 | 367 mil. € | 5 | 5 | |||||
12 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R 11,5/120 | 553 mil. € | 5 | 5 | |||||
12 úsekov |
253,1 km |
2 - 6 |
2 193 mil. € |
3,8 |
3,9 |
7/2020 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku