dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||||
1 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R2 východ | 93 mil. € | 9,8 km | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R4 sever | 133 mil. € | 8,9 km | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||||
3 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R4 sever | 124 mil. € | 8,3 km | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R4 sever | 101 mil. € | 6,3 km | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R6 Púchov - ČR | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | |||||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R6 Púchov - ČR | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | |||||||
7 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R1 BB - RK | Korytnica 930 m | 406 mil. € | 7 784 | 4 | 4 | 5/2033 (+10,2) | ||||||
7 úsekov |
65,3 km |
2 - 4 |
1 260 mil. € |
33,3 km |
2 561 - 10 032 | 4,0 |
3,4 |
9/2032 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku