dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 11,4 mil. € | 4 001 | 3 | 3 | 6/2027 (+4,7) | ||||||
2 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Biela Skala 630 m | 199 mil. € | 24,0 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | |||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 9,5 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 16,7 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 16,6 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 16,9 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
7 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 16,2 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||||
8 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 19,7 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||||
8 úsekov |
70,3 km |
2 |
1 148 mil. € |
16,3 mil. € |
2 561 - 10 032 | 3,6 |
3,3 |
6/2027 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku