18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
17,3 mil. € |
15,6 mil. € |
3 247 - 14 648 | 3,5 |
4,0 |
|||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 28,7 mil. € | 27,4 mil. € | 8 780 - 11 203 | 3 | 4 | ||||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 10,2 mil. € | 9,4 mil. € | 4 | 4 | ||||||
3 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 12,1 mil. € | 11,4 mil. € | 4 | 4 | ||||||
4 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 23,3 mil. € | 18,7 mil. € | 12 862 | 3 | 4 | |||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 22,0 mil. € | 16,5 mil. € | 12 157 | 3 | 4 | |||||
6 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 28,6 mil. € | 25,7 mil. € | 14 176 - 14 186 | 2 | 4 | |||||
7 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 10,2 mil. € | 9,3 mil. € | 6 969 - 10 726 | 4 | 4 | |||||
8 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 11,8 mil. € | 10,8 mil. € | 6 412 - 8 112 | 4 | 4 | |||||
9 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 62,1 mil. € | 59,4 mil. € | 3 | 4 | ||||||
10 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 8,9 mil. € | 7,9 mil. € | 5 587 | 5 | 4 | |||||
11 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 11,7 mil. € | 9,0 mil. € | 8 634 - 11 116 | 2 | 4 | |||||
12 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 20,4 mil. € | 17,7 mil. € | 7 793 | 2 | 4 | |||||
13 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 117 mil. € | 8,4 mil. € | 7,2 mil. € | 5 809 - 8 826 | 5 | 4 | |||||
14 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 406 mil. € | 35,3 mil. € | 33,4 mil. € | 7 784 | 4 | 4 | |||||
15 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 35,6 mil. € | 33,4 mil. € | 9 704 - 13 715 | 4 | 4 | |||||
16 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 13,5 mil. € | 11,8 mil. € | 5 762 - 14 648 | 4 | 4 | |||||
17 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | R 11,5/70 | 54 mil. € | 31,7 mil. € | 28,7 mil. € | 7 972 | 3 | 4 | |||||
18 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 611 mil. € | 10,4 mil. € | 9,2 mil. € | 3 247 - 11 434 | 4 | 4 | |||||
18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
17,3 mil. € |
15,6 mil. € |
3 247 - 14 648 | 3,5 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku