dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
-0,6 km |
3,5 |
4,0 |
|||||||||
1 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 0,2 km | 3 | 4 | 7,0 | ||||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Dolný Štál | 227 mil. € | 4 | 4 | 5,0 | |||||
3 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | Zemné | 172 mil. € | 4 | 4 | 6,0 | |||||
4 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | Mníchova Lehota | 59 mil. € | 0,7 km | 3 | 4 | 6,0 | ||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | -0,8 km | 3 | 4 | 7,0 | |||||
6 | 25. | 1/2026 | D3 | 10,8 km | 4 | Krásno nad Kysucou a Oščadnica (obe jednostranné) | 309 mil. € | 0,0 km | 2 | 4 | 6,0 | ||||
7 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 0,1 km | 4 | 4 | 5,0 | |||||
8 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | -0,8 km | 4 | 4 | 5,0 | |||||
9 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 4,0 | ||||||
10 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | -0,5 km | 5 | 4 | 4,0 | |||||
11 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 4,0 | ||||||
12 | 41. | 9/2028 | R2 | 11,5 km | 2 | Jerichov | 235 mil. € | 0,6 km | 2 | 4 | 5,0 | ||||
13 | 47. | 7/2029 | R2 | 14,0 km | 2 | Drienovec | 117 mil. € | 0,0 km | 5 | 4 | 4,0 | ||||
14 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | Liptovská Osada | 406 mil. € | 4 | 4 | 3,0 | |||||
15 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 3,0 | ||||||
16 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 4 | 4 | 2,0 | ||||||
17 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 3 | 4 | 4,0 | ||||||
18 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | Devičie, Dolné Semerovce | 611 mil. € | 4 | 4 | 2,0 | |||||
18 úsekov |
283,3 km |
2 - 4 |
4 893 mil. € |
-0,6 km |
3,5 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku