dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
17 úsekov |
171,7 km |
2 - 6 |
3 452 mil. € |
2 541 - 93 344 | 1,5 |
1,9 |
5/2017 - 10/2021 | ||||||||||
1 | 10/2013 | D3 | 12,3 km | 2 | Svrčinovec 420 m | 377 mil. € | 2 541 - 3 501 | 2 | 2 | 6/2017 | |||||||
2 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | Čerbrať - z pôv. 2026 m sa predĺži na cca 3600 m | Hubová, Likavka, Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | 1 | ||||||
3 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | Ovčiarsko 2360 m | 517 mil. € | 23 579 - 28 413 | 2 | 3 | 1/2021 (0,0) | ||||||
4 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | Višňové 7445 m | Lietavská Lúčka | 555 mil. € | 22 691 - 32 334 | 1 | 2 | ||||||
5 | 6/2014 | D3 | 4,3 km | 4 | D 24,5/80 | Považský Chlmec 2218 m | Brodno - dočasná | 269 mil. € | 28 413 - 37 927 | . . . | 4 | 2 | 12/2017 | ||||
6 | 8/2014 | R2 | 7,9 km | 4 | 88 mil. € | 14 357 - 15 923 | 1 | 1 | 5/2017 | ||||||||
7 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | Šamorín, Holice | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | |||||||
8 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | Čierna voda, Rača | 1 | 2 | |||||||||
9 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 2 | |||||||
10 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | Dunajská Lužná | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | |||||||
11 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | Prievoz | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 | ||||||
12 | 11/2016 | D1 | 14,4 km | 4 | D 26,5/120 | Budimír (Košice-Sever), Košické Olšany, Bidovce | 241 mil. € | 3 166 - 11 562 | 2 | 2 | 12/2019 (0,0) | ||||||
13 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | Čadca Podzávoz, Čadca Bukov | 269 mil. € | 11 465 - 18 743 | 1 | 2 | 12/2020 (0,0) | ||||||
14 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | Prešov 2244 m | Prešov západ, Prešov juh | 434 mil. € | 19 072 - 21 988 | 1 | 2 | 10/2021 | |||||
15 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 14 624 | 1 | 1 | 1/2021 (0,0) | |||||||
16 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | Bikoš 1153 m | Prešov - sever | 179 mil. € | 15 837 - 18 098 | 1 | 3 | ||||||
17 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | Mýtna | 142 mil. € | 9 007 - 9 998 | 2 | 2 | |||||||
17 úsekov |
171,7 km |
2 - 6 |
3 452 mil. € |
2 541 - 93 344 | 1,5 |
1,9 |
5/2017 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku